Fast Track Prefab for Scioto Downs Casino

The Scioto Downs Casino is a fast track project. The construction of the building must be concluded in six months, with all HVAC and plumbing finished in months two and three of the project.

Bruner Corporation has performed many fast track jobs in the past, but not as short as this. In order to accomplish this task, prefabrication was a necessity. Bruner developed an aggressive plan that entailed the prefabrication of all ductwork and plumbing fixture rough-in piping systems in our shops. The fixtures would subsequently be shipped to the project on a just-in-time basis.

The prefabrication process consisted of 60,000 pounds of ductwork and 2,500 feet of waste and vent, and domestic water piping. Modular restroom assemblies were prefabbed for 161 fixtures. Twenty-one batteries were shipped to the project, rolled in to place, and finish piped in four weeks.

Bruner met our commitment to our customer with the detailed planning and coordination between our fab shop and field teams.

Thanks to all those who made this project a tremendous success.